MGE Energy Inc MGEE
New risk paragraphs, branching off last year
Each branch is a paragraph in Risk Factors with nothing like it in the 10-K filed Feb 25, 2025. A box jumps to the paragraph as filed, below.
Paragraphs with nothing like them in last year's 10-K
7 paragraphs in Risk Factors of the 10-K filed Feb 24, 2026 with nothing like them in the 10-K filed Feb 25, 2025. Quoted exactly. Paragraphs that were only edited are under 10-K change.
Failure to comply with applicable regulations may result in customer refunds, penalties, and other payments which could materially and adversely affect our financial condition, results of operations, and liquidity.
recovery planning. Compliance with these standards affects our operating costs and any noncompliance could result in sanctions, including monetary penalties.
Demand for electricity and gas associated with existing data centers, and data centers developed in the future, could have a material impact on our operations.
We serve a variety of industries, including customers with large load requirements, such as data centers and other facilities. At this time, our service area does not include any large-scale data centers. The recent and ongoing expansion of data centers associated with increasing demand for artificial intelligence (AI) and other cloud‑based services is a national trend. This trend could lead to a significant increase in demand for electricity and gas if data centers expand or are developed within our service area over the next several years, which could require a rapid and significant increase in generation capacity and the development of related infrastructure. Alternatively, demand for electricity and gas could be lower than currently expected if the expansion of data centers and the associated increase in demand does not develop as anticipated.
We continue to evaluate the potential impacts of the development, construction, and operation of new data centers in our service area and will continue to evaluate potential mitigants to these risks, which could materially impact our operations, financial
condition and results of operations. However, we cannot predict whether the data centers under consideration will ever commence operations in our service area or the size of the load obligations of data centers that do become operational. Furthermore, the City of Madison has enacted a temporary moratorium on the development of new large-scale data centers to evaluate their impact on local infrastructure and resources, which may delay or prevent the commencement of operations for planned projects within the City of Madison. Other pending or future legislative or regulatory actions may also impact the development, construction and operation of new data centers in our service area.
Our revenues and the timing of cost recovery could be adversely impacted by improvements in power generation, storage, and use of technology to minimize energy use. Advancements in distributed generation, including commercial and residential solar installations and commercial micro turbines, continue to improve the cost-effectiveness of customer self-supply of electricity. Similarly, improvements in energy storage technology, such as batteries and fuel cells, enable customers to meet their around-the-clock electricity needs without relying on the electricity we provide.
Paragraphs in the 10-Q filed Nov 4, 2026 that were not in the one before
New in the latest 10-Q
35 paragraphs in the 10-Q filed Nov 4, 2026 with nothing like them in the 10-Q filed Aug 5, 2026 (at least half the words must differ; new numbers alone do not count). Quoted exactly, grouped by the item heading above them. This is text that changed, not a judgement of how serious it is.
Financial statements and notes
As of September 30, 2026, MGE Energy and MGE had revolving credit facilities with aggregate commitments of $50 million and $130 million, respectively. As of September 30, 2026, no borrowings were outstanding under these facilities.
Read in the 10-Q
On October 1, 2026, MGE Energy and MGE entered into third amended and restated credit agreements (collectively, the Third Amended and Restated Credit Agreements), which amended and restated their existing revolving credit facilities to, among other things, (i) extend the maturity dates to October 1, 2031 and (ii) increase the aggregate commitment under MGE's revolving credit facilities from $130 million to $250 million. MGE Energy's revolving credit commitment remained $50 million.
Read in the 10-Q
The Third Amended and Restated Credit Agreements contain customary representations and warranties, covenants and events of default. Each of the Third Amended and Restated Credit Agreements requires the borrower thereunder to maintain a ratio of consolidated indebtedness to consolidated total capitalization not to exceed 0.65 to 1.00. The ratio calculation excludes assets, liabilities, revenues, and expenses included in a borrower's financial statements as the result of the consolidation of "variable interest entities."
Read in the 10-Q
A change in control constitutes a default under each of the Third Amended and Restated Credit Agreements. Change in control events are defined in each of the Third Amended and Restated Credit Agreements as (i) a failure by MGE Energy to hold 100% of the outstanding voting equity interest in MGE or (ii) the acquisition of beneficial ownership of 30% or more of the voting power of the outstanding voting stock of MGE Energy by one person or two or more persons acting in concert.
Read in the 10-Q
In September 2026, the EPA published a final rule repealing the May 2024 rule's carbon dioxide emission guidelines for existing fossil fuel-fired units while retaining the efficiency-based requirements for new natural gas-fired combustion turbines. The September 2026 rule will go into effect on November 16, 2026, after which MGE's existing fossil fuel-fired generating units will no longer be subject to the GHG requirements of the May 2024 rule. Both the September 2026 final rule and the May 2024 rule are under legal challenge.
Read in the 10-Q
Show the other 30
Also in September 2026, the EPA published a proposed rule that would rescind the EPA's findings supporting the regulation of GHG emissions from fossil fuel-fired power plants under Section 111 of the Clean Air Act and repeal all remaining Section 111 GHG standards for fossil fuel-fired electric generating units, including the efficiency-based requirements for new natural gas-fired combustion turbines. MGE will continue to monitor this rulemaking.
Read in the 10-Q
In February 2026, the EPA finalized a rule rescinding its 2009 findings of contribution and endangerment for GHG emissions under Section 202(a) of the Clean Air Act and repealing all GHG emission standards for light-duty, medium-duty, and heavy-duty vehicles and engines. EPA concluded that it lacks statutory authority to regulate GHG emissions in response to global climate change concerns under Section 202(a)(1). The scope and timing of any impacts of this decision on federal GHG regulation under the Clean Air Act remain uncertain pending litigation and potential further agency action. MGE will continue to monitor developments.
Read in the 10-Q
In October 2026, the EPA notified the State of Wisconsin of its intended approach for area designations under the revised PM2.5 NAAQS. The EPA indicated that Milwaukee County is being considered for designation as a nonattainment area and provided the State an opportunity to submit additional information before final designations are issued. Final area designations are expected by February 2027, unless modified through ongoing administrative or judicial proceedings.
Read in the 10-Q
review of fuel costs completed in the year following the deferral. The following table summarizes deferred electric fuel-related costs:
Read in the 10-Q
Realized Losses (Gains) 2026 2025 (In thousands) Fuel for Electric Generation/ Purchased Power Cost of Gas Sold Fuel for Electric Generation/ Purchased Power Cost of Gas Sold Three Months Ended September 30: Commodity derivative contracts $ 174 $ - $ 288 $ - FTRs 1,161 - 262 - Nine Months Ended September 30: Commodity derivative contracts $ (392) $ (2,231) $ 884 $ (203) FTRs 929 - 860 -
Read in the 10-Q
Certain counterparties extend MGE a credit limit. If MGE exceeds these limits, the counterparties may require collateral to be posted. As of both September 30, 2026, and December 31, 2025, no counterparties were in a net liability position.
Read in the 10-Q
Nonperformance of counterparties to the non-exchange traded derivatives could expose MGE to credit loss. However, MGE enters into transactions only with companies that meet or exceed strict credit guidelines, and it monitors these counterparties on an ongoing basis to mitigate nonperformance risk in its portfolio. As of September 30, 2026, no counterparties had defaulted.
Read in the 10-Q
Level 3 - Pricing inputs are unobservable and reflect management's best estimate of what market participants would use in pricing the asset or liability.
Read in the 10-Q
The carrying amount of cash, cash equivalents, and outstanding commercial paper approximates fair market value due to the short maturity of those investments and obligations. The estimated fair market value of long-term debt is based on quoted market prices for similar financial instruments. Since long-term debt is not traded in an active market, it is classified as Level 2. The estimated fair market value of the financial instruments are as follows:
Read in the 10-Q
Columbia Energy Dome(b)(e) 19% Storage 3.4 MW $22 million(k)(l) $7.1 million 2028
Read in the 10-Q
Transmission investment income increased primarily due to higher equity earnings from MGE Transco's investment in ATC.
Read in the 10-Q
• Increased customer accounts costs are primarily due to higher costs associated with customer-related technology systems and supporting activities.
Read in the 10-Q
• Electric distribution costs increased, primarily due to higher system maintenance and operating costs, including overhead line maintenance and increased locating services.
Read in the 10-Q
The following table shows MGE Energy's forecasted capital expenditures for 2026 through 2031:
Read in the 10-Q
Includes actual capital expenditures already incurred in 2026 and estimated capital expenditures for the remainder of the year.
Read in the 10-Q
Forecasted capital expenditures are based upon management's assumptions with respect to future events, including the timing and amount of expenditures associated with environmental compliance initiatives, legislative and regulatory action, supply chain and market disruptions, customer demand and support for electrification and renewable energy resources, energy conservation programs, load growth, the timing of any required regulatory approvals, and the adequacy of rate recovery. Actual events may differ materially from these assumptions and result in material changes to those forecasted amounts.
Read in the 10-Q
Forecasted capital expenditures reflect the following significant generation and storage projects that are currently under construction or pending regulatory approval:
Read in the 10-Q
Other local solar and battery storage projects: In 2026 through 2028, electric renewable capital expenditures include local investments in solar generation and battery storage. Forecasted total capital expenditures for those years are approximately $46 million.
Read in the 10-Q
As of September 30, 2026, MGE Energy and MGE had revolving credit facilities with aggregate commitments of $50 million and $130 million, respectively.
Read in the 10-Q
On October 1, 2026, MGE Energy and MGE entered into third amended and restated credit agreements which amended and restated their existing revolving credit facilities to, among other things, (i) extend the maturity dates to October 1, 2031 and (ii) increase the aggregate commitment under MGE's revolving credit facilities from $130 million to $250 million. MGE Energy's revolving credit commitment remained $50 million.
Read in the 10-Q
Item 6
N.A. and U.S. Bank National Association, as Syndication Agents (incorporated by reference to Exhibit 10.2 to the Current Report on Form 8-K filed by MGE Energy and MGE with the U.S. Securities and Exchange Commission on October 5, 2026).
Read in the 10-Q
10.3 Third Amended and Restated Credit Agreement dated as of October 1, 2026, among Madison Gas and Electric Company, the Lenders party thereto, U.S. Bank National Association, as Administrative Agent, and Associated
Read in the 10-Q
Bank, N.A., as Syndication Agent (incorporated by reference to Exhibit 10.3 to the Current Report on Form 8-K filed by MGE Energy and MGE with the U.S. Securities and Exchange Commission on October 5, 2026).
Read in the 10-Q
31.1 Certifications Pursuant to Rules 13a-14(a) and 15d-14(a) of the Securities Exchange Act of 1934 filed by Jeffrey M. Keebler for MGE Energy, Inc.
Read in the 10-Q
31.2 Certifications Pursuant to Rules 13a-14(a) and 15d-14(a) of the Securities Exchange Act of 1934 filed by Jared J. Bushek for MGE Energy, Inc.
Read in the 10-Q
31.4 Certifications Pursuant to Rules 13a-14(a) and 15d-14(a) of the Securities Exchange Act of 1934 filed by Jared J. Bushek for Madison Gas and Electric Company
Read in the 10-Q
32.1 Certifications Pursuant to Section 1350 of Chapter 63 of Title 18 United States Code (Sarbanes-Oxley Act of 2002) filed by Jeffrey M. Keebler for MGE Energy, Inc.
Read in the 10-Q
32.2 Certifications Pursuant to Section 1350 of Chapter 63 of Title 18 United States Code (Sarbanes-Oxley Act of 2002) filed by Jared J. Bushek for MGE Energy, Inc.
Read in the 10-Q
32.3 Certifications Pursuant to Section 1350 of Chapter 63 of Title 18 United States Code (Sarbanes-Oxley Act of 2002) filed by Jeffrey M. Keebler for Madison Gas and Electric Company
Read in the 10-Q
32.4 Certifications Pursuant to Section 1350 of Chapter 63 of Title 18 United States Code (Sarbanes-Oxley Act of 2002) filed by Jared J. Bushek for Madison Gas and Electric Company
Read in the 10-Q
The 10-Q's risk factors against the 10-K
Item 1A of the 10-Q filed Nov 4, 2026 against Item 1A of the 10-K filed Feb 24, 2026.
A 10-Q repeats only the risks that changed, so a 10-K paragraph that is missing from it is not counted as removed.
Added is a paragraph with nothing like it in the 10-K, Reworded a sentence that is in both with several words changed,
Quiet changes a sentence in both where one to four words changed and one is a hedge or a modal
(cut words struck through, new words highlighted).
Text on the page, not a score; each links to the filing at sec.gov.
What the 10-Q itself says about its risk factors:There were no material changes from the risk factors disclosed in Item 1A. Risk Factors in our 2025 Annual Report on Form 10-K, other than as set forth below:
Read in the 10-Q
Phrases used for the first time
Two-word phrases in Risk Factors of the 10-K filed Feb 24, 2026 that are in none of the 1 earlier 10-Ks stored, back to Feb 25, 2025
Where each one is used
- data centers: Demand for electricity and gas associated with existing data centers, and data centers developed in the future, could have a material impact on our operations.
- local state: Our business is subject to regulation at the local, state, and federal levels. The regulations adopted by local, state, and federal agencies affect how we do business, our ability to undertake specified actions since pre-approval or authorization may be required for projects, the costs of operations, and the rates...
- resource plans: MGE is subject to oversight and monitoring by MISO. Changes in MISO's resource adequacy process, including seasonal reserve margin requirements and capacity accreditation rules, impact how generating facilities, such as MGE's solar projects, are recognized for capacity. New methodologies, like the direct...
- eligibility requirements: We have historically reduced our consolidated federal and state income tax liability through various tax credits. We may not be able to fully use these tax credits if future taxable income is insufficient or if transferability options are limited. Any future disallowance of credits due to legislative changes or...
- large-scale data: We serve a variety of industries, including customers with large load requirements, such as data centers and other facilities. At this time, our service area does not include any large-scale data centers. The recent and ongoing expansion of data centers associated with increasing demand for artificial intelligence...
- development construction: We continue to evaluate the potential impacts of the development, construction, and operation of new data centers in our service area and will continue to evaluate potential mitigants to these risks, which could materially impact our operations, financial
- new data: We continue to evaluate the potential impacts of the development, construction, and operation of new data centers in our service area and will continue to evaluate potential mitigants to these risks, which could materially impact our operations, financial
- enable customers: Our revenues and the timing of cost recovery could be adversely impacted by improvements in power generation, storage, and use of technology to minimize energy use. Advancements in distributed generation, including commercial and residential solar installations and commercial micro turbines, continue to improve the...
Used at least twice, small words left out. Counted, not picked: a phrase can be new because the company renamed something.
What was taken out
3 paragraphs of last year's Risk Factors with nothing like them now. The longest are quoted.
Sources
Item 1A of each 10-K and 10-Q on EDGAR, quoted exactly. Each paragraph links to the filing at sec.gov.