Marked against last year's 10-K:
cut words struck through, new words highlighted and underlined.
MD&A 142 words changed in this paragraph; it is 39% similar to last year's version.
Retention Incentive Program: Under its Clean Energy Plan, Consumers will retire the The retirement of J.H. Campbell coal-fueled generating units in 2025. In order is subject to ensure necessary staffing at J.H. Campbell through retirement, temporary extensions under emergency orders issued by the U.S. Secretary of Energy. As a result, Consumers has implemented a retention incentive program. The aggregate cost of the J.H. Campbell program through 2025 is estimated measures to be less than $50 million; Consumers ensure appropriate staffing levels and expects to recognize $5 incur up to $4 million during each 90‑day emergency order period. Consumers will seek recovery of these retention benefit costs in 2025. The MPSC has approved deferred accounting treatment from FERC, consistent with rate recovery sought for these costs; these expenses are deferred as a regulatory asset. other costs of complying with the emergency orders. For additional details on this program, see Item 8. Financial Statements and Supplementary Data—Notes to the Consolidated Financial Statements—Note 19, 20, Exit Activities and Asset Sales. For additional details on the emergency orders, see Item 8. Financial Statements and Supplementary Data—Notes to the Consolidated Financial Statements—Note 3, Regulatory Matters.
Source: Item 7, 10-K 0000811156-26-000004 vs Item 7, 10-K 0000811156-25-000036
Risk Factors 133 words changed in this paragraph; it is 66% similar to last year's version.
Consumers has announced a long-term strategy for delivering clean, reliable, resilient, and affordable energy, including a plan to end the use of coal in owned generation in 2025, and other subsidiaries of CMS Energy have plans to develop and operate clean energy assets. The MPSC, FERC, other regulatory authorities, or other third parties may prohibit, delay, or impair some or all of CMS Energy’s and Consumers’ planned acquisitions or development of owned or purchased electric generation and storage capacity. Consumers’ planned electric generation capacity, including renewable generation or storage projects, may be adversely impacted by interconnection delays at MISO or in the footprints of other regional transmission organizations, and/or by interconnection costs. CMS Energy and Consumers and its contractors may be unable to acquire, site, construct timely, and/or permit generation and storage capacity, including some or all of the generation and storage capacity proposed in Consumers’ plan. CMS Energy and Consumers’ ability to implement their plans may be affected by environmental regulations, global supply chain disruptions, import tariffs, and changes in the cost, availability, and supply of generation and storage capacity. While CMS Energy and Consumers continue to advocate for advances in commercially available technologies required to reduce or eliminate greenhouse gases on a cost-effective basis at scale, such advances are largely outside of CMS Energy’s and Consumers’ control. Advancements in technology related to items such as battery storage, carbon capture/storage, and electric vehicles may not become commercially available or economically feasible as projected. Customer programs such as energy efficiency and demand response may not realize the projected levels of customer participation.
Source: Item 1A, 10-K 0000811156-26-000004 vs Item 1A, 10-K 0000811156-25-000036
Legal Proceedings 80 words changed in this paragraph; it is 68% similar to last year's version.
In order to enforce their rights under the contract and parent guaranty, and to pursue appropriate damages, Consumers and DTE Electric filed a complaint against TAES and Toshiba in the U.S. District Court for the Eastern District of Michigan in 2022. TAES and Toshiba filed a motion to dismiss the complaint, along with an answer and counterclaims seeking approximately $15 million in damages related to payments allegedly owed under the parties’ contract. As a co-owner of Ludington, Consumers would be liable for 51 percent of any such damages, if liability and damages were proven. The court denied the motion to dismiss filed by TAES and Toshiba. The parties are engaged in ongoing litigation, including discovery, pursuant to a court-ordered schedule. Consumers believes the counterclaims filed by TAES and Toshiba are without merit, but cannot predict the financial impact or outcome of this matter. An unfavorable outcome could have a material adverse effect on CMS Energy’s and Consumers’ financial condition, results of operations, or liquidity.
Source: Item 3, via Note 4 – Contingencies and Commitments, 10-K 0000811156-26-000004 vs Item 3, via Note 3 – Contingencies and Commitments, 10-K 0000811156-25-000036
Accounting Policies 19 words changed in this paragraph; it is 87% similar to last year's version.
Cash and Cash Equivalents and Restricted Cash and Cash Equivalents: Cash and cash equivalents include short-term, highly liquid investments with original maturities of three months or less. Restricted cash and cash equivalents are held primarily for the repayment of securitization bonds and funds held in escrow. Cash and cash equivalents may also be restricted to pay other contractual obligations such as leasing of coal railcars. These amounts are classified as current assets since they relate to payments that could or will occur within one year.
Source: Item 8, Note 1 – Significant Accounting Policies, 10-K 0000811156-26-000004 vs Item 8, Note 1 – Significant Accounting Policies, 10-K 0000811156-25-000036